The High Stakes of a Simple Street Crossing
For most people, crossing the street is a mindless part of a daily routine, but for those at Chandler Hall Health Services, it’s a high-stakes game of “Frogger.” Staff members balancing meal trays and parents gripping the hands of toddlers must time their gaps in traffic perfectly to navigate South Sycamore Street. This road effectively bisects the campus, creating a dangerous logistical divide for residents and employees alike.
As of July 31, 2026, the situation has reached a boiling point. Despite a petition signed by over 100 community members [view the petition] and initial board approval at the October 8, 2025, Board of Supervisors meeting, the project remains at a total standstill. What began as a straightforward plea for pedestrian safety has spiraled into a complex standoff between local advocacy and municipal bureaucracy.
My analysis of the April 2026 Treasurer’s Report [read the analysis] may shed some light on another reason for a delay. Township spending is purposely kept under budget despite overruns by cutting back services provided by other departments such as engineering—for example, traffic studies and surveys undertaken in preparation for approved projects.
As discussed in that article, some members of the public have questioned why the township has been so slow in beginning preliminary work on approved pedestrian safety projects. Now they know why!
A Crosswalk That Serves Everyone from Toddlers to Seniors

The South Sycamore Street crossing is a vital artery for a uniquely vulnerable, multi-generational population. This isn't just a standard neighborhood street; the diverse physical needs of the pedestrians here make safety upgrades non-negotiable.
- Chandler Hall Residents: Seniors with slower gait speeds who require more time to clear a lane of traffic.
- Meal-Service Employees: Staff who must frequently cross the asphalt while carrying heavy trays and supplies.
- Daycare Children: Toddlers whose small stature makes them less visible to drivers and whose movements can be sudden and unpredictable.
- YMCA Users: Local families and fitness enthusiasts who increase the overall foot traffic of the area.
Because this crossing serves both the very young and the elderly, the margin for driver error is razor-thin. Resident Charles Feuer underscored the gravity of the situation during a public comment session:

“The importance of the safety of that crosswalk in Newtown is real.”— Charles Feuer
The Frustrating “10-Month Silence”
As mentioned above, in October 2025, the Newtown Township Board of Supervisors authorized township engineers to begin preparing cost estimates and design options. At the time, the authorization was hailed as a major victory for the 100-plus advocates who had spent months pushing for the change.
However, as we sit in late July 2026, there is no visible sign of progress. This 10-month gap between official “approval” and any physical action has turned initial optimism into deep-seated resident frustration. Feuer noted that it is becoming increasingly difficult to tell the community to remain patient when there is nothing to show for a year of waiting.
“We got the board’s approval to get an estimate and get it going and now it’s 10 months later and there’s not much I’m able to tell them except that I’m told it’s in the works.”— Charles Feuer
The PennDOT Paradox: A Bureaucratic Catch-22
The most significant hurdle is a classic bureaucratic catch-22 involving the Pennsylvania Department of Transportation (PennDOT). Residents have requested state-of-the-art “rapid rectangular flashing beacons” (RRFBs) and pedestrian-activated buttons to force drivers to take notice.
The irony is that installing this advanced safety equipment may actually “kill” the crosswalk in its current location. According to Board Chair Ed Merriman, PennDOT regulations may require the township to relocate the crossing to the nearest intersection if these lights are installed. This would move the crossing away from the heart of the Chandler Hall campus, forcing seniors and daycare groups to walk even further to cross a road that already divides their facilities.
The High-Stakes Game of “Grant Math”
Funding this project is a matter of “grant math,” and the stakes for the township’s budget are high. The Board is currently navigating two very different financial paths:
PennDOT Multimodal Transportation Fund: This traditional route requires the municipality to provide a 30% financial match for the total project cost, which can quickly add up to tens of thousands of taxpayer dollars.
DCED Program: Administered by the Department of Community and Economic Development, this program has waived all match requirements through 2027. The township has a proven track record here, having successfully used these “zero-match” funds for the Newtown-Yardley sidewalk and curb project.
Despite the obvious benefits of the DCED program, the Board is hesitant to apply until the project scope is finalized. Merriman expressed concern that if they secure a grant before the PennDOT relocation issue is solved, the township could be legally committed to a project they aren't fully prepared to execute.
“It’s Just How Government Works”: The Slow Road to 2027
The current status of the project is a sobering reality check for those seeking urgent change. The Board of Supervisors is now looking toward the 2027 budget cycle to address these upgrades. For a resident who signed a petition in early 2025, this represents a nearly three-year wait for a few strips of paint and a set of flashing lights.
As Ed Merriman summarized at the close of a recent meeting:
“It feels slow but it’s kind of how government can work.”— Ed Merriman, Newtown Township Board Chair
While the Board focuses on coordinating with state agencies and ensuring fiscal correctness, the daily risk to pedestrians remains.
Please refer to the original article upon which this post is based: